May-11-09

Multi-Use Recreation Complex Pre-Qualification

As of Monday May 11, 2009 Amherstburg Council approved a recommendation by the Project Steering Committee and confirms the following four submissions as the successful pre-qualified firms for the submission of request for proposals for the new Multi-Use Recreation Complex:

Ball Construction
DeAngelis Construction
EllisDon
Giffels Corporation

And Further, that council, having reviewed the request for proposals specifics, authorize the Project Development Managers and the Steering Committee to make any necessary revisions as requested and issue the request for proposals document to the Pre-Qualified firms on or before Monday May 18, 2009.

Schedule as follows:

Short list design-build firms/teams
Monday May 11th, 2009

 

Issue RFP to pre-qualified design-build firms/teams
Tuesday May 19th, 2009  
 

Design Build RFP Closes
Monday July 6th, 2009

 

Award design-build contract
Monday July 20th, 2009

 

Substantial completion
Friday Sept 10th, 2010


The authorized contact person for this RFP Process is:

 

Edward M. Pavao, Amherstburg Recreation Project Manager

Nustadia Recreation Inc.

Phone: 905-318-5111 ext 224

Email: epavao@nustadia.com



staff